Staff numbers :
80
Form of contract:
JCT 2005 D&B
Client sector:
Professional Advisory
Contract value:
£740K
       
Project duration:
9 Weeks
Floor area:
900m2

Client brief:
KPMG appointed Paramount to undertake the fit out of their new corporate headquarters in Cardiff Waterside. The key project objectives were the delivery of high quality space to serve the needs of in-house staff and to create client meeting facilities in keeping with KPMG’s expectation as a major corporate consultancy organisation. The project’s scope encompassed the design and fitting out of open plan office space, client meeting rooms, video conferencing facilities, bespoke servery and staff breakout areas, with high levels of environmental control throughout.

Scope of works:
• Detail Design Development
• Project Management
• Bespoke Joinery
• Partitioning, Ceilings and Flooring
• M & E Design

“Paramount exceeded our expectations, and I was impressed by their can do attitude and attention to detail. They delivered on time and to budget and I would not hesitate to use Paramount again.”
Robert Moss – Project Manager, KPMG.

“Paramount’s significant experience in working in BREEAM Excellent buildings, along with their previous experience of
working in 3 Assembly Square in particular were key factors which led us to select Paramount as our delivery partners. We made the right decision in selecting both the building and Paramount. Our staff have settled in very well and I’ve nothing but very positive feedback from them."

Simon Jones – Senior Partner, KPMG

 
CHAS Copyright 2003