Projects | Reliance Security Group, Llantrisant

Staff numbers :
120
Form of contract:
JCT
Client sector:
Security Sector
Contract value:
£200K
       
Project duration:
6 Weeks
Floor area:
1300m2

Client brief:
Reliance Security Group appointed Paramount to provide a turnkey design and build solution for the fitting-out and
furnishing of their new offices in Talbot Green , Llantrisant. Paramount worked closely with Reliance Security to ensure that the design brief and program of works were achieved within the budget and time scales given.

Scope of works:
• Project Management
• Space Planning and Interior Design
• M & E Design and Modifications
• Partitioning, Ceilings and Flooring
• Haworth Furniture

“We were please with Paramount’s approach and commitment to our project, which was shown from start to finish.”
Iain Bacon - Reliance Security Group

 